|
Future Plan of Capacity Addition
A total 86,600 kW capacity addition has been
targeted as under:
| Project |
District |
Capacity(KW) |
Year
of Completion |
|
1
Asiganga-I |
Uttarkashi |
4500 |
2009-10 |
|
2
Asiganga-II |
Uttarkashi |
4500 |
2010-11 |
|
3
Asiganga-III |
Uttarkashi |
7300(under revision) |
2010-11 |
|
4
Dunao |
Pauri Garhwal |
1500 |
2009-10 |
|
5
Shobla-I |
Pithoragarh |
8000 |
2010-11 |
|
6
Tankul |
Pithoragarh |
12000 |
2010-11 |
|
7
Kaliganga-I |
Rudraprayag |
4000 |
2009-10 |
|
8
Kaliganga-II |
Rudraprayag |
6000 |
2010-11 |
|
9
Madhyamaheshwar |
Rudraprayag |
10000 |
2009-10 |
|
10
Kalidigad |
Uttarkashi |
9000 |
2010-11 |
|
11
Sonegad |
Uttarkashi |
3000 |
2010-11 |
|
12
Suringad II |
Pithoragarh |
5000 |
2010-11 |
|
13
Urgam II |
Chamoli |
3800 |
2010-11 |
|
14
Painagad |
Pithoragarh |
4000 |
2010-11 |
|
15
Pilangad II |
Uttarkashi |
4000 |
2010-11 |
|
|
|
86,600 |
|
The Setting up of SHPs in the state of Uttarakhand
would help in the overall development of the state
especially in the remote areas in the hills. It is
a known fact that supplying improved energy
services to people for the first time is
difficult, supplying such services profitably to
very poor people who live far away from roads and
the electricity grid poses a particularly
difficult challenge. Nevertheless, the access to
electricity in the remote areas would generate
livelihood and the impact can be spread to
marginalized people and then to social activities.
UJVNL is in the process of proposing new SHPs for
CDM for earning Emission Reduction credits which
will generate additional revenue for SHPs and make
them financially viable. "It is easier to make the
profitable social, than to make the social
profitable" and UJVNL is aware that in planning
SHP investments it is important to consider the
plant for securing livelihood at an early stage
and then to see how the impact can be spread to
masses and for social activities. UJVNL is
endeavoring to set up the SHPs so as bring about
development in the remote areas of Uttarakhand
there by facilitating overall development of the
state.
Strategy for future capacity addition
(a) Presently, UJVNL takes up the
construction of the SHPs only after carrying out
detailed survey(s), investigation(s) and
engineering including cost optimization of various
options. This requires collection of Hydrological
and geological data besides synthesizing the same
for arriving at a most economical engineering
option. The entire work is outsourced to reputed
agencies for timely completion besides maintaining
the quality of work. Based on the past experience
of the geology, metrology and the topography, safe
designs have been adopted and where ever found
necessary power channels have been replaced by
tunnels.
(b) Some of the other improvements in
the process of development of SHPs are that:-
I. Geological Surveys are being conducted in thorough manner so as to
locate the
power station at a safe place making it less
prone to natural calamities.
II. Power Channels are more prone to land
slides/cloud bursting etc, therefore the water
conductor system is being changed to tunnel as
per site specific conditions.
III. Machines of simple design are planned
to be used for the power stations located in
far off areas for their easy operation &
maintenance.
IV. Staff posted at these power stations is
being given proper training in the operation &
maintenance so as to minimize the break down
time.
|