The Galogi Hydropower station is one of the oldest
running power house in the country and
therefore, a part of Indian national heritage. It is located on River Bhatta and Kiyarkurli
near Mussoorie about 22 km from Dehradun. It has 2 machines (Pelton)
of 0.5 MW(800HP) each installed in 1907 & 2 machines of 1
MW(1600HP) each installed in 1933 manufactured by Boving
& Co.,London.1MW units are marked as units 1&2 and the 0.5 MW
ones as unit 3 &4. Power house building is surface type, Gross head available is 285m & Design
Discharge 1.36 cumecs.

UJVNL proposes to
carry out the M&U of the power station which is estimated to cost Rs. 12.28 crore. The
major M&U works proposed are:-
•
Refurbishment of existing generating units
•
Replacement of penstock and associated
civil works.
MNES, Government of India has revised its incentive schemes to
take into account development of SHP projects up to 25 MW &
commissioned seven years prior to the date of the request of the
proposal submitted to the MNES.The existing
equipment/works of Galogi SHP are in poor
condition and need repair, retroffing and
replacement are required so as to enable harnessing of the water power
potential. The RMU of this project will contribute to
·
Utilization of water power potential and
providing environ-friendly electricity to the nearby area.
·
Help meeting power requirement of the
concerned power supply system.
·
Promoting tourism in the valley.
·
Preserving heritage related to early years
of the last century.
The M&U works
would increase the generation to 12 MU besides enhancing the life of
plant and the works are expected to be completed by 2009-10.
|
Year
|
2004-05
|
2005-06
|
2006-07
|
2007-08
|
2008-09
(Upto Nov-08)
|
|
Generation(MU)
|
3.61
|
3.40
|
3.23
|
3.68
|
2.17
|

|